Monday, 28 March 2016

Braskem Sign a Contract to Supply Ethane from US

Click on the following links for more story:


Wednesday, 23 March 2016

China’s Saudi Oil Imports in February Hit Near Record High

Click on the following links for more story:




Thursday, 17 March 2016

Kolon & BASF Sign a Agreement to Set up JV for POM in South Korea



Click on the following links for more story:

Wednesday, 16 March 2016

RIL to invest Rs 13,000 crore in petrochemical expansion-IV: Execution in 27 months flat

Project execution will include engineering, procurement, construction, installation and start-up of facilities.
 
8The Basic engineering package shall be provided by Reliance Project Management Group (RPMG) in consultation with Reliance R&D Department.
 
8Detailed Engineering for this project shall be executed by the Mumbai Engineering Center (MEC).
 
8Procurement will be done with the help of RIL's internal Procurement and Contracts department.
 
8Engineering deliverables for procurement such as SOQ for construction contracts, MRs for all tagged equipment and PR for all bulk items shall be developed by MEC.
 
8Construction of above ground structures such as equipment foundations, control building for the proposed CPVC, VCM, PVC & ethane storage tank project shall be executed under the responsibility of the site construction department of RIL by appointing various contractors.
 
8The construction contractors will include all disciplines, such as civil, structural, mechanical, piping, electrical and instrumentation. Vendor services will be taken for specialized equipment during the construction and commissioning phase.
 
8Project Schedule: Overall completion schedule envisaged for this project is 27 months with a two month grace period.


Click here for more information

RIL to invest Rs 13,000 crore in petrochemical expansion-III: Project management details

Project execution will include engineering, procurement, construction, installation and start-up of facilities.
 
8The Basic engineering package shall be provided by Reliance Project Management Group (RPMG) in consultation with Reliance R&D Department.
 
8Detailed Engineering for this project shall be executed by the Mumbai Engineering Center (MEC).
 
8Procurement will be done with the help of RIL's internal Procurement and Contracts department.
 
8Engineering deliverables for procurement such as SOQ for construction contracts, MRs for all tagged equipment and PR for all bulk items shall be developed by MEC.
 
8Construction of above ground structures such as equipment foundations, control building for the proposed CPVC, VCM, PVC & ethane storage tank project shall be executed under the responsibility of the site construction department of RIL by appointing various contractors.
 
8The construction contractors will include all disciplines, such as civil, structural, mechanical, piping, electrical and instrumentation. Vendor services will be taken for specialized equipment during the construction and commissioning phase.
 
8Project Schedule: Overall completion schedule envisaged for this project is 27 months with a two month grace period.


Click here for more information.

RIL to invest Rs 13,000 crore in petrochemical expansion-II: Details of utility requirements

The RIL expansion will be also entail investments in utilities that will involve the the treatment and distribution of raw water. steam/condensate, cooling water, DM water, fire water, compressed air, nitrogen and oxygen, hydrogen, fuel gas and a power plant.
 The following systems will have to be put into place:
 
8Air Separation Unit
 
8Compressed air system
 
8DM water plant
 
8Raw water
 
8Cooling towers
 
8Captive Power Plant
 
8Fire water system
 
8Tank farm
 
8Effluent Treatment Plant (ETP)


Click here for more information.

RIL to invest Rs 13,000 crore in petrochemical expansion-I: Expansion will raise capacity across the board

Who says big investments are not taking place in the oil & gas and related segments in India?
 
8Close on the heels of news that money is going to be pumped into the KG Basin to get deepwater gas discoveries off the ground, RIL has unfolded a massive Rs 13,250 crore plan to expand its gas craker at Bharuch in Gujarat, based on imported propane.
 The expansion will raise the company's petrochemical capacity in the following manner:
 
8Ethylene capacity will go up by a hefty 200,000 tonnes
 
8Ethylene Dichloride by 89,000 tonnes
 
8Vinyl Chloride Monomer, Polyvinyl Chloride and Chlorine by 45,000 tonnes
 
8Caustic Soda by 52,000 tonnes
 
8Ethylene Oxide by 30,000 crore
 
8HDPE by Rs 2,000 tonnes
 
8Ethylene Vinyl Acetate by 2,000 tonnes
 New units are to be added as well, and that includes:
 
8A Chlorinated Poly Vinyl Chloride (CPVC) unit with a capacity of 70,000 tonnes
 
8A Vinyl Chloride Monomer of 12,00,000 tonnes
 
8A Poly Vinyl Cholride of a capacity of 12,00,00 tonnes.
 
8There will also be a concomitant increase in relevant product and byproduct capacities as well.


Click here for more information.